The UK has a new contender for one of its largest data centres, and a headline number that sounds bigger than the commitment behind it. What has been signed is a partnership to develop a site. The £20 billion figure is an estimate of potential spending if every phase is built, including the chips.
What was announced
Drax’s stock exchange announcement says it agreed to develop a partnership with Brookfield and Radiant, Brookfield’s UK-headquartered AI infrastructure platform, for a data centre on the Drax Power Station estate in North Yorkshire. Capital comes through a Brookfield–Qai joint venture. The site has about 4GW of grid access and 2.6GW of dispatchable generation.
- Phase 1: up to 100MW using grid power, targeting commercial operations from early 2028. Radiant will try to secure anchor customers before construction starts. A planning application is being prepared, with public consultation expected to begin in November 2026.
- Phase 2: an “ambition” for 500MW between 2028 and 2031, powered behind the meter by Drax’s own generation under a long-term PPA, subject to consents. Drax’s 2025 Contract for Difference already includes a mechanism to request up to 500MW for a data centre, subject to agreement with the UK Government and the Low Carbon Contracts Company.
- Phase 3: further capacity after 2031. Together the phases could reach gigawatt scale.
The conditions
Drax says Phase 1 is “subject to the necessary planning approvals,” regulatory and network approvals, “securing an acceptable tenant for the project,” commercial agreements, and “each party taking a final investment decision.” CNBC puts the conditions the same way and reports that Drax shares rose 8.8% in early trading. BBC News described the project as having “secured £20bn backing”. Drax’s own press-release headline also says “£20bn partnership”, but its stock-exchange announcement says Brookfield “estimates that total potential investment, including semiconductor chips, could exceed £20 billion.”
The pushback
The BBC quotes Owen Espley of Global Action Plan, who said the extra demand would “make it impossible” to meet clean energy targets. His group wants a moratorium on new projects. A government spokesperson pointed to the new Data Centre Covenant on water use, energy costs and community benefits.
Our read
Reusing a power station’s grid connection and generation is the smartest available answer to the UK’s grid-connection queue. CNBC notes reports that Microsoft pulled out of anchoring an Nscale site near London amid grid-connection delays. But until there is a tenant and a final investment decision, this is a 100MW option, not a gigawatt campus. Watch the November consultation and any anchor-customer news. See also Europe buys its own frontier.